Combined-cycle power plant - cable basement compartmentation
- Client type
- EPC contractor, utility client (GCC)
- Scope
- 1,850 penetrations across 42 rated bulkheads, 2-hour compartmentation
Problem
Cable trays crossing basement fire walls had been sealed with non-tested material during construction. The consultant rejected the package: no system numbers, no T ratings and no record of what was behind each seal.
Solution
We resurveyed every crossing, mapped it to a tested MVL system by substrate and tray fill, and specified a coated batt and ablative coating system with intumescent sealant at annular gaps. Installers were trained on the tested detail before work restarted.
Result
Full 2-hour F and T rating reinstated, package accepted first submission, and an as-built register issued with a photographic record for each of the 1,850 references.
- UL 1479 (ASTM E814)
- 2 h F and T rating
- Civil defence approved